Jupiters U.S. One Bridge News

Img

The latest update regarding Jupiter’s U.S. One bridge is that it may be postponed. The Jupiter U.S. One bridge may not close for replacement until 2023. 

The temporary detour for the bridge construction will begin in the spring of 2023 and will take approximately 20 months. Construction is scheduled to be complete in mid-2025. Click HERE for the complete article.

To view the Jupiter Presentation for the Jupiter U.S. 1 Bridge Replacement Project, please click HERE.

Additional information regarding the project can be located on the Town of Jupiter website at: https://www.jupiter.fl.us/1658/FDOT-Project-on-the-US1-Bridge  and on the Florida Department of Transportation website: https://www.fdot.gov/projects/jupiterus1bridge/main

Start Date:Summer 2021Estimated Full Bridge Closure Start Date:Spring 2023  Estimated Project Completion Date:Summer 2025 Cost:$136 million